- 1 July 2017: Projects Begin.
- 31 January 2018: Mid-year one progress report due.
- March 2018: Present project’s progress at the Interdepartmental Hurricane Forum and meet with NHC points of contact.
- 1 June 2018: PIs make preparations for and begin real-time testing and evaluation during 2018 hurricane season.
- 31 July 2018: Annual report due (Year 1).
- July 2018: Second year of funded activity for renewed projects begins.
- 31 January 2019: Mid-year two report projects due.
- March 2019: Present project’s progress at the Interdepartmental Hurricane Forum.
- 1 June 2019: PIs make preparations for and begin real-time testing and evaluation during 2019 hurricane season.
- 31 July 2019: Final reports due.
- December 2019: Decision on operational implementation of the all projects by the NHC Director.